GATE 2023 · AR · MSQ · 2 marks · Part B1: Architecture › Professional Practice, Estimation & Tendering
GATE 2023 Architecture and Planning question: Select the statement(s) that are TRUE regarding ‘Quality and Cost-Based Selection…
Select the statement(s) that are TRUE regarding ‘Quality and Cost-Based Selection (QCBS)’ system for tendering.
- (A)
Financial bid is opened before technical bid.
- (B)
Earnest Money Deposit (EMD) is submitted before the opening of technical bid.
- (C)
Technically qualified bidder with lowest financial bid is always awarded the job.
- (D)
A composite scoring system considering both the financial and technical bids is adopted for awarding the job.
Show answer
Official answer: B,D
Practise this question with exam-style marking