GATE 2023 · AR · MSQ · 2 marks · Part B1: Architecture › Professional Practice, Estimation & Tendering

GATE 2023 Architecture and Planning question: Select the statement(s) that are TRUE regarding ‘Quality and Cost-Based Selection…

Select the statement(s) that are TRUE regarding ‘Quality and Cost-Based Selection (QCBS)’ system for tendering.

  1. (A)

    Financial bid is opened before technical bid.

  2. (B)

    Earnest Money Deposit (EMD) is submitted before the opening of technical bid.

  3. (C)

    Technically qualified bidder with lowest financial bid is always awarded the job.

  4. (D)

    A composite scoring system considering both the financial and technical bids is adopted for awarding the job.

Show answer

Official answer: B,D