GATE 2023 Architecture and Planning question: Select the correct sequence of activities for transit-operation planning process.

Select the correct sequence of activities for transit-operation planning process.

  1. (A)

    Network Route Design → Timetable Development → Vehicle Scheduling → Crew Scheduling

  2. (B)

    Timetable Development → Crew Scheduling → Vehicle Scheduling → Network route design

  3. (C)

    Vehicle Scheduling → Crew Scheduling → Network Route Design → Timetable Development

  4. (D)

    Crew Scheduling → Vehicle Scheduling → Timetable Development → Network Route Design

Show answer

Official answer: A