GATE 2023 set1 · CE · NAT · 2 marks · Water Resources Engineering › Hydrology

GATE 2023 set1 Civil Engineering question: In Horton’s equation fitted to the infiltration data for a soil, the initial…

In Horton’s equation fitted to the infiltration data for a soil, the initial infiltration capacity is 10 mm/h; final infiltration capacity is 5 mm/h; and the exponential decay constant is 0.5 /h. Assuming that the infiltration takes place at capacity rates, the total infiltration depth (in mm) from a uniform storm of duration 12 h is ____________. (round off to one decimal place)

Show answer

Official answer: 69.7 to 70.1