GATE 2023 Chemical Engineering question: A design engineer needs to purchase a membrane module (M) for a plant. Details about the…
A design engineer needs to purchase a membrane module (M) for a plant. Details about the two available options, M1 and M2, are given in the table below. The overall plant has an expected life of 7 years. If the interest rate is 8 % per annum, compounded annually, the difference in the net present value (NPV) of these two options, in lakhs of rupees, is ______ (rounded off to one decimal place).
| M1 | M2 | |
|---|---|---|
| Purchase cost (in lakhs of rupees) | 10 | 5 |
| Expected life (years) | 5 | 3 |
Show answer
Official answer: -4.8 to -4.6 or 4.6 to 4.8