GATE 2023 · ME · MCQ · 1 mark · Industrial Engineering › Inventory Control

GATE 2023 Mechanical Engineering question: With reference to the Economic Order Quantity (EOQ) model, which one of the options…

With reference to the Economic Order Quantity (EOQ) model, which one of the options given is correct?

figure

  1. (A)

    Curve P1: Total cost, Curve P2: Holding cost, Curve P3: Setup cost, and Curve P4: Production cost.

  2. (B)

    Curve P1: Holding cost, Curve P2: Setup cost, Curve P3: Production cost, and Curve P4: Total cost.

  3. (C)

    Curve P1: Production cost, Curve P2: Holding cost, Curve P3: Total cost, and Curve P4: Setup cost.

  4. (D)

    Curve P1: Total cost, Curve P2: Production cost, Curve P3: Holding cost, and Curve P4: Setup cost.

Show answer

Official answer: A