GATE 2023 Mining Engineering question: In project scheduling techniques, the CORRECT statement is

In project scheduling techniques, the CORRECT statement is

  1. (A)

    Both CPM and PERT are deterministic.

  2. (B)

    Both CPM and PERT are probabilistic.

  3. (C)

    CPM is deterministic and PERT is probabilistic.

  4. (D)

    CPM is probabilistic and PERT is deterministic.

Show answer

Official answer: C