GATE 2023 Mining Engineering question: A workshop has four tasks and equal number of machines to perform the tasks. Each of the…
A workshop has four tasks and equal number of machines to perform the tasks. Each of the machines can perform only one of the four tasks. The estimated cost at each of the machines to complete each task is given in table
| MACHINE | T1 | T2 | T3 | T4 |
|---|---|---|---|---|
| M1 | 10 | 40 | 60 | 30 |
| M2 | 90 | 70 | 100 | 90 |
| M3 | 40 | 50 | 110 | 70 |
| M4 | 80 | 70 | 80 | 50 |
The total cost of optimal assignment is_____.
[rounded off to 1 decimal place]
Show answer
Official answer: 210