A build-up test is characterized by production at constant rate over time, tp, followed by shut-in period of Δt. A plot of shut-in bottom hole pressure (Pws) with Log [(tp+Δt)/(Δt)] for pressure build-up test data is shown in the figure.

Which of the following statement(s) is/are TRUE?
- (A)
Early Time Region (ETR): Pressure build-up data is affected by reservoir boundaries and other reservoir heterogeneities such as sealing faults
- (B)
Middle Time Region (MTR): Pressure build-up data is reached after end of the wellbore storage and the pressure transient has entered the virgin reservoir
- (C)
Late Time Region (LTR): Pressure build-up data is affected by reservoir boundaries and other reservoir heterogeneities such as sealing faults
- (D)
Middle Time Region (MTR): Pressure build-up data is affected by reservoir boundaries and other reservoir heterogeneities such as sealing faults
Show answer
Official answer: B,C