After well completion, a discovery well in an oil reservoir is produced for a short period and then closed for pressure build-up test. The production history before shut-in is given below.

Production rate (STB/day) Duration (days)
500 5
550 7
400 8

The Horner’s pseudo-producing time, , is__________hr (rounded to nearest integer).