GATE 2023 Petroleum Engineering question: After well completion, a discovery well in an oil reservoir is produced for a short…
After well completion, a discovery well in an oil reservoir is produced for a short period and then closed for pressure build-up test. The production history before shut-in is given below.
| Production rate (STB/day) | Duration (days) |
|---|---|
| 500 | 5 |
| 550 | 7 |
| 400 | 8 |
The Horner’s pseudo-producing time, , is__________hr (rounded to nearest integer).
Show answer