GATE 2023 Production and Industrial Engineering question: The standard time for completing a job on a machine is 10 minutes. Number of machines…
The standard time for completing a job on a machine is 10 minutes. Number of machines available is 5, each machine is available for 300 hours/month, and average machine utilization is 80 %. The maximum number of jobs that can be produced in a month is _____ (in integer).
Show answer
Official answer: 7200