GATE Assistant

Past questions › Production and Industrial Engineering › GATE 2023

GATE 2023 · PI · NAT · 1 mark · Industrial Engineering › Method Study & Work Measurement

GATE 2023 Production and Industrial Engineering question: The standard time for completing a job on a machine is 10 minutes. Number of machines…

The standard time for completing a job on a machine is 10 minutes. Number of machines available is 5, each machine is available for 300 hours/month, and average machine utilization is 80 %. The maximum number of jobs that can be produced in a month is _____ (in integer).

Show answer

Official answer: 7200

Practise this question with exam-style marking