GATE 2023 Production and Industrial Engineering question: Six jobs (1, 2, 3, 4, 5, 6) undergo drilling, followed by reaming operation. The time…
Six jobs (1, 2, 3, 4, 5, 6) undergo drilling, followed by reaming operation. The time required for each operation is given as
| Job | Drilling (min) | Reaming (min) |
|---|---|---|
| 1 | 30 | 45 |
| 2 | 30 | 15 |
| 3 | 60 | 40 |
| 4 | 20 | 25 |
| 5 | 35 | 28 |
| 6 | 45 | 70 |
The sequence of processing the jobs, using the Johnson’s rule, is
Show answer
Official answer: A