GATE 2023 · PI · MCQ · 2 marks · Industrial Engineering › Facility Location & Layout

GATE 2023 Production and Industrial Engineering question: There are four locations (P, Q, R, S) and four factors to be considered for setting up a…

There are four locations (P, Q, R, S) and four factors to be considered for setting up a facility. The scores (on a scale of 0 to 10, with 10 being the maximum) for the given locations and the weight assigned to each factor are given as

Factor Weight P Q R S
Availability of raw material 0.4 6 8 5 4
Availability of skilled labor 0.3 7 4 10 6
Infrastructure 0.2 8 3 10 8
Proximity to market 0.1 10 8 7 5

The best location for setting up the facility is

  1. (A)

    P

  2. (B)

    Q

  3. (C)

    R

  4. (D)

    S

Show answer

Official answer: C