GATE 2023 Production and Industrial Engineering question: The work sampling study, with 100 observations, revealed 25 % idle time of a worker. The…
The work sampling study, with 100 observations, revealed 25 % idle time of a worker. The number of observations required for ±10 % accuracy and 95.45 % confidence level is _____ (in integer).
Show answer
Official answer: 71 to 76 or 1150 to 1210