GATE 2023 · PI · NAT · 2 marks · Industrial Engineering › Method Study & Work Measurement

GATE 2023 Production and Industrial Engineering question: The work sampling study, with 100 observations, revealed 25 % idle time of a worker. The…

The work sampling study, with 100 observations, revealed 25 % idle time of a worker. The number of observations required for ±10 % accuracy and 95.45 % confidence level is _____ (in integer).

Show answer

Official answer: 71 to 76 or 1150 to 1210