GATE 2023 Production and Industrial Engineering question: Details of activities of a project are given as Activity A B C D E F G H I J --- --- ---…
Details of activities of a project are given as
| Activity | A | B | C | D | E | F | G | H | I | J |
|---|---|---|---|---|---|---|---|---|---|---|
| Time (days) | 8 | 10 | 8 | 7 | 16 | 15 | 18 | 14 | 9 | 4 |
| Predecessors | - | - | - | A | A | B, D | C | C | F, G | E, I, H |
The time required, in days, to complete the project along the critical path is _____ (in integer).
Show answer
Official answer: 43