GATE 2024 Architecture and Planning question: Which of the following options is/are the right sequence(s) in water treatment process?
Which of the following options is/are the right sequence(s) in water treatment process?
- (A)
Coagulation → Flocculation → Sedimentation
- (B)
Sedimentation → Filtration → Disinfection
- (C)
Sedimentation → Flocculation → Coagulation
- (D)
Disinfection → Filtration → Flocculation
Show answer
Official answer: A,B