GATE 2024 · AR · NAT · 2 marks · Part B1: Architecture › Construction Planning, PERT & CPM

GATE 2024 Architecture and Planning question: The network diagram of a construction project is shown in the following Figure. The…

The network diagram of a construction project is shown in the following Figure. The duration of each activity, in days, and the early start time of the project are denoted in the diagram. The total project duration along the critical path, in days, is _____________(in integer).

figure

Show answer

Official answer: 18