GATE 2024 set1 Civil Engineering question: The total primary consolidation settlement (S c) of a building constructed on a 10 m…
The total primary consolidation settlement () of a building constructed on a 10 m thick saturated clay layer is estimated to be 50 mm. After 300 days of the construction of the building, primary consolidation settlement was reported as 10 mm. The additional time (in days) required to achieve 50% of will be ______________ (rounded off to the nearest integer).
Show answer
Official answer: 1550 to 1600