Consider the statements P and Q.

P: In a Pure project organization, the project manager maintains complete authority and has maximum control over the project.

Q: A Matrix organization structure facilitates quick response to changes, conflicts, and project needs.

Which one of the following options is CORRECT?

  1. (A)

    Both P and Q are TRUE

  2. (B)

    P is TRUE and Q is FALSE

  3. (C)

    Both P and Q are FALSE

  4. (D)

    P is FALSE and Q is TRUE

Show answer

Official answer: A