GATE 2024 set2 Civil Engineering question: Consider the statements P and Q. P: In a Pure project organization, the project manager…
Consider the statements P and Q.
P: In a Pure project organization, the project manager maintains complete authority and has maximum control over the project.
Q: A Matrix organization structure facilitates quick response to changes, conflicts, and project needs.
Which one of the following options is CORRECT?
Show answer
Official answer: A