GATE 2024 set2 Civil Engineering question: Consider the following data for a project of 300 days duration. Budgeted Cost of Work…
Consider the following data for a project of 300 days duration.
Budgeted Cost of Work Scheduled (BCWS) = Rs. 200
Budgeted Cost of Work Performed (BCWP) = Rs. 150
Actual Cost of Work Performed (ACWP) = Rs. 190
The ‘schedule variance’ for the project is
Show answer
Official answer: A