GATE Assistant

Past questions › Civil Engineering › GATE 2024 set2

GATE 2024 set2 · CE · MCQ · 1 mark · Structural Engineering › Construction Materials & Management

GATE 2024 set2 Civil Engineering question: Consider the following data for a project of 300 days duration. Budgeted Cost of Work…

Consider the following data for a project of 300 days duration.

Budgeted Cost of Work Scheduled (BCWS) = Rs. 200
Budgeted Cost of Work Performed (BCWP) = Rs. 150
Actual Cost of Work Performed (ACWP) = Rs. 190

The ‘schedule variance’ for the project is

  1. (A)

    (–)Rs. 50

  2. (B)

    (–)50 days

  3. (C)

    (+)Rs. 50

  4. (D)

    (+)50 days

Show answer

Official answer: A

Practise this question with exam-style marking

Discussion

No discussion yet.

Join the discussion