GATE 2024 set2 Civil Engineering question: To finalize the direction of a survey, four surveyors set up a theodolite at a station P…
To finalize the direction of a survey, four surveyors set up a theodolite at a station P and performed all the temporary adjustments. From the station P, each of the surveyors observed the bearing to a tower located at station Q with the same instrument without shifting it. The bearings observed by the surveyors are , , and . Assuming that each measurement is taken with equal precision, the most probable value of the bearing is
Show answer
Official answer: B