GATE Assistant

Past questions › Civil Engineering › GATE 2024 set2

GATE 2024 set2 · CE · NAT · 2 marks · Structural Engineering › Construction Materials & Management

GATE 2024 set2 Civil Engineering question: The table shows the activities and their durations and dependencies in a project.…

The table shows the activities and their durations and dependencies in a project.

Activity Duration (Days) Depends on
A 8 -
B 4 A
C 4 B
D 4 C, L
F 4 A
G 4 F
H 6 G, L
K 10 A
L 6 F, K

The total duration (in days) of the project is__________ (in integer).

Show answer

Official answer: 30

Practise this question with exam-style marking