The chart given below compares the Installed Capacity (MW) of four power generation technologies, T1, T2, T3, and T4, and their Electricity Generation (MWh) in a time of 1000 hours (h).

figure

The Capacity Factor of a power generation technology is:

Capacity Factor =

Which one of the given technologies has the highest Capacity Factor?

  1. (A)

    T1

  2. (B)

    T2

  3. (C)

    T3

  4. (D)

    T4