GATE 2024 set2 Geology and Geophysics question: The chart given below compares the Installed Capacity (MW) of four power generation…

The chart given below compares the Installed Capacity (MW) of four power generation technologies, T1, T2, T3, and T4, and their Electricity Generation (MWh) in a time of 1000 hours (h).

figure

The Capacity Factor of a power generation technology is:

Capacity Factor =

Which one of the given technologies has the highest Capacity Factor?

  1. (A)

    T1

  2. (B)

    T2

  3. (C)

    T3

  4. (D)

    T4

Show answer

Official answer: A