GATE 2024 Mechanical Engineering question: At the current basic feasible solution (bfs) v 0 ( v 0 R 5), the simplex method yields…

At the current basic feasible solution (bfs) (), the simplex method yields the following form of a linear programming problem in standard form.

Here the objective function is written as a function of the non-basic variables. If the simplex method moves to the adjacent bfs () that best improves the objective function, which of the following represents the objective function at , assuming that the objective function is written in the same manner as above?

  1. (A)

  2. (B)

  3. (C)

  4. (D)

Show answer

Official answer: A