GATE 2024 Mining Engineering question: A project network with the sequence of five activities is shown. The crashing costs of…

A project network with the sequence of five activities is shown.

figure

The crashing costs of activities are

Activity A B C D E
Duration (week) 5 6 8 3 4
Crashing cost per week (lakh INR) 4.0 2.5 2.0 3.0 4.0

If the project is crashed by one week, the increase in project cost, in lakh INR, is

  1. (A)

    2.0

  2. (B)

    2.5

  3. (C)

    3.0

  4. (D)

    4.0

Show answer

Official answer: B