GATE Assistant

Past questions › Mining Engineering › GATE 2024

GATE 2024 · MN · NAT · 2 marks · Engineering Mathematics › Probability & Statistics

GATE 2024 Mining Engineering question: A thermal power plant has an agreement with three mines M1, M2 and M3 to receive ‘Grade…

A thermal power plant has an agreement with three mines M1, M2 and M3 to receive ‘Grade 1’ coal, in the proportion of 60%, 25% and 15%, respectively. The probabilities that a wagon supplied coal to the plant containing below ‘Grade 1’ from mines M1, M2 and M3 are 0.02, 0.03 and 0.04, respectively. On a random check, a sample wagon is found to carry below ‘Grade 1’ coal. The probability that the wagon belongs to mine M1, is ______. (round off up to 2 decimals)

Show answer

Official answer: 0.42 to 0.52

Practise this question with exam-style marking

Discussion

No discussion yet.

Join the discussion