Which of the following tests is/are used to obtain reservoir deliverability () information?

  1. Exploration or appraisal well openhole wireline
  2. Exploration or appraisal well Drill Stem Test (DST)
  3. Development well openhole wireline
  4. Development well Drill Stem Test (DST)

: permeability,

: thickness of formation,

: viscosity of the oil

  1. (A)

    1 only

  2. (B)

    3 only

  3. (C)

    1 and 3

  4. (D)

    2 and 4

Show answer

Official answer: D