GATE 2024 Petroleum Engineering question: A choke is generally installed at the well head and/or downhole. The desired function(s)…

A choke is generally installed at the well head and/or downhole. The desired function(s) of the choke is/are to

  1. (A)

    protect surface equipment from damage.

  2. (B)

    avoid sand ingress problem.

  3. (C)

    regulate production rate.

  4. (D)

    ensure oil and water coning.

Show answer

Official answer: A,B,C