GATE 2024 Production and Industrial Engineering question: A repairable machine operated for 2400 hours in a year and for that year the machine…

A repairable machine operated for 2400 hours in a year and for that year the machine broke down 8 times. The mean time to repair including waiting time is found to be 20 hours for that year.

If the mean time to repair including waiting time could have been reduced to 10 hours for that year, then the improvement in the availability of that machine would be ___________ %. (Rounded off to 2 decimal places)

Show answer

Official answer: 3.19 to 3.23