GATE 2024 · PI · NAT · 2 marks · Industrial Engineering › Assembly Line Balancing & Material Handling

GATE 2024 Production and Industrial Engineering question: An assembly line consists of three work stations (S1, S2 and S3) in series to assemble a…

An assembly line consists of three work stations (S1, S2 and S3) in series to assemble a toy. The times required to perform tasks at these stations are 6, 4 and T minutes, respectively. If the efficiency of the assembly line in the steady state is 75%, then the maximum value of T (in minutes) is ____________. (Answer in integer)

Show answer

Official answer: 8