GATE 2024 TF Engineering Sciences question: A winder operates at 750 m/min with 93 % efficiency. Time (min) taken for the winder to…

A winder operates at 750 m/min with 93 % efficiency. Time (min) taken for the winder to wind 1.2 kg of 20 tex yarn is approximately

  1. (A)

    68

  2. (B)

    74

  3. (C)

    86

  4. (D)

    90

Show answer

Official answer: C