GATE 2025 Architecture and Planning question: Match the following items of work in Group-I with their corresponding units of…

Match the following items of work in Group-I with their corresponding units of measurement in Group-II.

Group-I Group-II
(P) Honeycomb Brickwork (1) Running Meter
(Q) Steel Reinforcement (2) Cubic Meter
(R) Brick on Edge (3) Square Meter
(S) Earthwork in Excavation (4) Kilogram
(5) Number
  1. (A)

    P–1, Q–4, R–3, S–2

  2. (B)

    P–3, Q–1, R–4, S–5

  3. (C)

    P–5, Q–2, R–1, S–4

  4. (D)

    P–3, Q–4, R–1, S–2

Show answer

Official answer: D