GATE 2025 Architecture and Planning question: A construction project consists of four activities. The duration, relationship and cost…
A construction project consists of four activities. The duration, relationship and cost parameters are given in the table. The indirect cost of the project is INR 5000/- per week. If the project has to be completed by 12 weeks, the total project cost will be, INR________________. (Answer in integer)
| Activity | Immediate Predecessor Activity | Normal Duration (Weeks) | Crash Duration (Weeks) | Normal Cost (INR) | Crash Cost (INR) |
|---|---|---|---|---|---|
| P | Nil | 8 | 5 | 20,000 | 26,000 |
| Q | Nil | 5 | 2 | 30,000 | 33,000 |
| R | P | 6 | 4 | 40,000 | 52,000 |
| S | Q | 4 | 3 | 10,000 | 13,000 |
Show answer
Official answer: 164000