A construction project consists of four activities. The duration, relationship and cost parameters are given in the table. The indirect cost of the project is INR 5000/- per week. If the project has to be completed by 12 weeks, the total project cost will be, INR________________. (Answer in integer)

Activity Immediate Predecessor Activity Normal Duration (Weeks) Crash Duration (Weeks) Normal Cost (INR) Crash Cost (INR)
P Nil 8 5 20,000 26,000
Q Nil 5 2 30,000 33,000
R P 6 4 40,000 52,000
S Q 4 3 10,000 13,000
Show answer

Official answer: 164000