To derive the total flood hydrograph at a catchment outlet from an isolated storm, the order in which the following methods are applied, from the first method to the last method, is

P. Obtaining the hyetograph

Q. Addition of baseflow

R. Estimation of initial and infiltration losses

S. Application of unit hydrograph

  1. (A)

    PRSQ

  2. (B)

    PQRS

  3. (C)

    RPSQ

  4. (D)

    PSQR

Show answer

Official answer: A