GATE 2025 set2 · CE · MSQ · 1 mark · Water Resources Engineering › Irrigation
GATE 2025 set2 Civil Engineering question: Pick one or more CORRECT statement(s) from the choices given below, in the context of…
Pick one or more CORRECT statement(s) from the choices given below, in the context of upstream and downstream cut-offs provided below the concrete apron of weirs / barrages constructed across alluvial rivers.
- (A)
Cut-offs are provided to increase the rate of flow over the weir / barrage.
- (B)
Cut-offs are provided to increase the seepage length and prevent failure due to piping.
- (C)
The bottom level of cut-offs mainly depends on the scour depth.
- (D)
Cut-offs are provided to ensure occurrence of hydraulic jump within the stilling basin.
Show answer
Official answer: B,C