GATE Assistant

Past questions › Civil Engineering › GATE 2025 set2

GATE 2025 set2 · CE · NAT · 2 marks · Structural Engineering › Construction Materials & Management

GATE 2025 set2 Civil Engineering question: The figure shows a network diagram for a construction project. The activities A, B, C,…

The figure shows a network diagram for a construction project. The activities A, B, C, D, E, and F are represented by arrows and their durations are in the figure.

figure

The total float available for the activity E in day(s) is equal to _____ (round off to the nearest integer).

Show answer

Official answer: 1

Practise this question with exam-style marking

Discussion

No discussion yet.

Join the discussion