GATE 2025 set2 Civil Engineering question: The figure shows a network diagram for a construction project. The activities A, B, C,…
The figure shows a network diagram for a construction project. The activities A, B, C, D, E, and F are represented by arrows and their durations are in the figure.

The total float available for the activity E in day(s) is equal to _____ (round off to the nearest integer).
Show answer
Official answer: 1