GATE 2025 · ME · NAT · 2 marks · Industrial Engineering › PERT & CPM

GATE 2025 Mechanical Engineering question: A project involves eight activities with the precedence relationship and duration as…

A project involves eight activities with the precedence relationship and duration as shown in the table below. The slack for the activity D is _____ hours (answer in integer).

Activity Immediate predecessor Duration (hours)
A - 4
B A 8
C A 5
D B 2
E B 7
F C 6
G D 3
H E, F, G 9
Show answer

Official answer: 2