GATE 2025 Mechanical Engineering question: A project involves eight activities with the precedence relationship and duration as…
A project involves eight activities with the precedence relationship and duration as shown in the table below. The slack for the activity D is _____ hours (answer in integer).
| Activity | Immediate predecessor | Duration (hours) |
|---|---|---|
| A | - | 4 |
| B | A | 8 |
| C | A | 5 |
| D | B | 2 |
| E | B | 7 |
| F | C | 6 |
| G | D | 3 |
| H | E, F, G | 9 |
Show answer
Official answer: 2