GATE 2025 Mining Engineering question: The relevant information on metal extraction from a copper mine are given below Selling…

The relevant information on metal extraction from a copper mine are given below

Selling price of copper (Rs./kg) = 900

Mining cost (Rs./tonne of ore) = 500

Processing cost (Rs./tonne of ore) = 2000

Overall recovery of copper metal (%) = 70

Ignoring all other costs, the breakeven cutoff grade of copper, in %, is ______ (rounded off to 2 decimal places)

Show answer

Official answer: 0.38 to 0.42