GATE 2025 Mining Engineering question: Following information are given for three mines of a company receiving explosives from…
Following information are given for three mines of a company receiving explosives from three suppliers.
| Explosive transportation cost (Rs./tonne) | |||||
|---|---|---|---|---|---|
| Mine-1 | Mine-2 | Mine-3 | Supply capacity (tonne) | ||
| Explosive suppliers | Supplier - S | 10 | 15 | 50 | 2500 |
| Supplier - O | 5 | 2 | 100 | 2500 | |
| Supplier - I | 30 | 40 | 20 | 3000 | |
| Explosive demand (tonne) | 1000 | 2000 | 5000 |
Considering the initial basic feasible solution of this transportation problem, using North-West corner method, the transportation cost of explosives supplied to the company, in Rs., is
Show answer
Official answer: C