GATE 2025 · MN · NAT · 2 marks · Mining Methods and Machinery › Wire Ropes, Haulages & Conveyors

GATE 2025 Mining Engineering question: A direct rope haulage has the following details Output = 24 tonne/hour Length of trip =…

A direct rope haulage has the following details

Output = 24 tonne/hour

Length of trip = 610 m

Gradient = 1 in 12

Capacity of mine car = 1.0 tonne

Tare weight of mine car = 0.5 tonne

Average rope speed = 1.694 m/s

Change over time of cars = 3 minute

Acceleration due to gravity = 10.0 m/s

Neglecting all frictional resistance and mass of the rope, the minimum power required, in kW, to raise the loaded mine cars is ______ (rounded off to 3 decimal places)

Show answer

Official answer: 11 to 14