GATE 2025 Mining Engineering question: Data from a borehole log with collar elevation at 590 mRL are given below. Composite…

Data from a borehole log with collar elevation at 590 mRL are given below. Composite grade is calculated using cores of 5 m above and below the reference bench at 580 mRL. The composite grade, in %, is ___ (rounded off to 1 decimal place)

Sequence of cores (top to bottom) Core length (m) Grade (%)
1 3.0 40
2 3.0 42
3 2.0 41
4 3.0 43
5 2.0 42
6 3.0 41
7 3.0 44
Show answer

Official answer: 41 to 42

Practise this question with exam-style marking