GATE 2025 · MN · NAT · 2 marks · Mining Methods and Machinery › Underground Coal Mining

GATE 2025 Mining Engineering question: A double ended ranging drum (DERD) shearer uni-directionally cuts coal in a longwall…

A double ended ranging drum (DERD) shearer uni-directionally cuts coal in a longwall panel having the following details

Shearer drum diameter = 1.4 m

Panel dimension = 1200 m × 200 m × 2.4 m

Web depth = 0.6 m

Average cutting speed = 5 m/minute

Average retreating speed = 10 m/minute

Average operational delay between cuts is 2 hour. There are two production shifts, each of 8 hour duration. The number of days required for complete extraction of the panel is ____ (in integer)