GATE 2025 Petroleum Engineering question: For a hydrocarbon reservoir, the following parameters are used in the general material…

For a hydrocarbon reservoir, the following parameters are used in the general material balance equation (MBE).

= Initial (original) oil in place, stb

= Initial volume of gas cap, scf

= Ratio of initial volume of gas cap to volume of oil initial in place, rb/rb

= Initial water saturation

= Initial oil saturation

= Initial oil formation volume factor, rb/stb

= Initial gas formation volume factor, rb/scf

The total pore volume (in rb) of the reservoir is

  1. (A)

  2. (B)

  3. (C)

  4. (D)

Show answer

Official answer: C