GATE 2025 · PI · MCQ · 2 marks · Operations research and Operations management › Project Management: CPM & PERT

GATE 2025 Production and Industrial Engineering question: The network diagram of eight activities (A to H) along with their time durations (in…

The network diagram of eight activities (A to H) along with their time durations (in days, given in bracket) of a project is shown in the figure. The critical path of the project is

figure

  1. (A)

    1−2−3−6

  2. (B)

    1−4−3−6

  3. (C)

    1−5−6

  4. (D)

    1−4−5−6

Show answer

Official answer: B