GATE 2025 Production and Industrial Engineering question: A product has to be manufactured in a single-line layout by carrying out the six tasks…

A product has to be manufactured in a single-line layout by carrying out the six tasks in a sequence. The time (in minute) of the six sequential tasks are 37, 8, 19, 34, 36 and 17. These tasks cannot be further sub-divided. For minimizing the cycle time, the number of stations to be used is________. (Answer in integer)