GATE 2025 Production and Industrial Engineering question: The solidification of a casting starts at 10 AM. However, the solidification of the…
The solidification of a casting starts at 10 AM. However, the solidification of the molten metal at the center-line of the mold starts at 10:03 AM and ends at 10:10 AM. The casting is considered solidified completely when the solidification is completed at the center-line of the mold. The center-line feeding resistance (CFR) in percentage is________. (Answer in integer)
Show answer
Official answer: 70