GATE 2026 Architecture and Planning question: A construction project consists of 7 activities. These activities, their connecting…

A construction project consists of 7 activities. These activities, their connecting events, and the three PERT times (optimistic, likely, and pessimistic), in days, are listed in the table below. The project starts on 27th July 2026. Assuming no holidays for the entire duration of the project except 15th August 2026, the expected date of completion of the project will be _____________ August 2026 (mention the date in integer).

Activity Connecting Events Three PERT Times (in Days)
P 1 → 2 4 – 6 – 8
Q 1 → 3 5 – 6 – 13
R 2 → 5 6 – 8 – 22
S 2 → 3 8 – 11 – 14
T 3 → 5 2 – 4 – 12
U 3 → 4 4 – 8 – 18
V 4 → 5 5 – 7 – 15
Show answer

Official answer: 30