GATE 2026 · ME · MCQ · 2 marks · Industrial Engineering › Production Planning & Scheduling

GATE 2026 Mechanical Engineering question: Four jobs are on order in a factory. As on day 20 of the production calendar, the…

Four jobs are on order in a factory. As on day 20 of the production calendar, the corresponding due date and work remaining to complete these jobs (in days) are given in the table below.

Job Due date Work remaining (in days)
M 26 5
N 24 10
O 28 10
P 31 5

Which job(s) has/have critical ratio less than unity?

  1. (A)

    Job N and Job O

  2. (B)

    Job M and Job N

  3. (C)

    Job P

  4. (D)

    Job O and Job P

Show answer

Official answer: A