GATE 2026 Mechanical Engineering question: Four jobs are on order in a factory. As on day 20 of the production calendar, the…
Four jobs are on order in a factory. As on day 20 of the production calendar, the corresponding due date and work remaining to complete these jobs (in days) are given in the table below.
| Job | Due date | Work remaining (in days) |
|---|---|---|
| M | 26 | 5 |
| N | 24 | 10 |
| O | 28 | 10 |
| P | 31 | 5 |
Which job(s) has/have critical ratio less than unity?
Show answer
Official answer: A