GATE 2026 Mechanical Engineering question: The activities of a PERT network and their corresponding activity time estimates (in…
The activities of a PERT network and their corresponding activity time estimates (in weeks) i.e., optimistic (), most likely (), and pessimistic () are given in the table below.
| Activity | |||
|---|---|---|---|
| 1−2 | 2 | 4 | 12 |
| 1−3 | 2 | 4 | 6 |
| 1−4 | 3 | 4 | 11 |
| 2−5 | 3 | 6 | 9 |
| 3−4 | 2 | 5 | 14 |
| 3−5 | 3 | 3 | 3 |
| 4−5 | 3 | 6 | 15 |
| 5−6 | 2 | 5 | 8 |
The expected project length is ________ weeks (in integer).
Show answer
Official answer: 22