GATE 2026 Mechanical Engineering question: The activities of a PERT network and their corresponding activity time estimates (in…

The activities of a PERT network and their corresponding activity time estimates (in weeks) i.e., optimistic (), most likely (), and pessimistic () are given in the table below.

Activity
1−2 2 4 12
1−3 2 4 6
1−4 3 4 11
2−5 3 6 9
3−4 2 5 14
3−5 3 3 3
4−5 3 6 15
5−6 2 5 8

The expected project length is ________ weeks (in integer).

Show answer

Official answer: 22