GATE 2026 Mining Engineering question: The expected time (P days) and standard deviation (Q days) of the different activities…
The expected time (P days) and standard deviation (Q days) of the different activities (A to F) in a project are indicated in the network diagram as (P, Q). The standard deviation of the project completion time, in days, is __________. (rounded off to one decimal place)